What we did
The vessel's hose handling crane needed its periodic load test while the ship lay at Khor Fakkan anchorage.
We first examined the structure and components, checked mechanical condition and tested the controls and safety devices, so the crane was known to be ready before loading.
The crane was then tested against its safe working load using the approved load table, and passed.